National Prosecutor's Office – new headquarters to be completely renovated. It cost almost PLN 80 million, and it was supposed to be PLN 15 million

Must read

- Advertisement -


No matter where you look, some procedure was violated and huge amounts of money were spent, said Borys Budka (PO), commenting on the irregularities revealed by the Supreme Audit Office in connection with the purchase of its headquarters by the National Prosecutor's Office. The guest of “Fakty po Faktach” pointed out that a building had been purchased “which immediately had to be converted.” Therefore, it cost not PLN 15, but almost PLN 80 million – he emphasized. The investigation into this case is being conducted by the Warsaw regional prosecutor's office.

Supreme Chamber of Control published information on post-audit conclusions regarding the purchase of the headquarters by the National Prosecutor's Office in 2017. According to the Supreme Audit Office, PK bought the headquarters without a reliable assessment of its technical condition and the scope of necessary reconstruction. The Chamber reported that it required spending over PLN 76 million on renovation – more than four times more than planned. According to NIK, it was initially assumed that the cost would amount to PLN 15 million. The investigation into this case is being conducted by the Regional Prosecutor's Office in Warsaw.

Budka: It was the National Prosecutor's Office. Which prosecutor would dare to file charges?

These findings were commented on Thursday in “Fakty po Faktach” on TVN24 by the former head of the Ministry of State Assets, an MP elected to the European Parliament in the new term. Borys Budka (AFTER).

- Advertisement -

– Strangely enough, Mr. (Zbigniew – ed.) Ziobro again. Such an impeccable sheriff, an impeccable man who thought he could do anything – he was ironic. According to the former head of MAP, “the beginning of this pathological system was Ziobro's takeover of the prosecutor's office.” – Let me remind you that in March 2016, regulations came into force and Ziobro became the head of the prosecutor's office again. But not to chase down bandits, but to have insight into every procedure, to be able to influence it and to feel impunity, he said.

Budka said it was “the purchase of a building that immediately had to be converted.” – They thought it was 15 million. It cost 79 million. Well, then someone could have pressed charges? After all, it was the National Prosecutor's Office. Which prosecutor would dare to file charges? – He was asking.

The TVN24 guest emphasized that “there is one more aspect” of this case. – This mechanism of non-tender renovation was based on the fact that it was commissioned to a special institution, which was also subordinate to the Minister of Justice, the Prison Service. She had no competences, so she had to hire subcontractors. Only without a tender procedure again – he pointed out.

In his opinion, “pathology followed pathology”. – No matter where you turn, some procedure was violated and huge amounts of money were spent – added Budka.

National Prosecutor's Office, headquarters at ul. Progress 3Albert Zawada/PAP

Findings of the Supreme Audit Office. PK “did not make a credible assessment”

The Supreme Audit Office reported that it concerned the property at ul. Postępu 3 in Warsaw, where the headquarters of the National Prosecutor's Office is located. The Chamber assessed that, before purchasing this property for its headquarters, PK “did not make a reliable assessment of its technical condition and a reliable estimate of the amount of expenditure necessary to incur its reconstruction and adaptation to its needs.”

“As a result, the decision to purchase was made in violation of the principle of spending in a purposeful, economical manner that allows for obtaining the best results from the expenditure incurred. The reconstruction planning and its implementation were carried out without due diligence in the organization of supervision and then the manner of its performance over key participants of the construction process,” the chamber reported.

NIK recalled that until December 28, 2017, the National Prosecutor's Office did not have its own headquarters and rented rooms of the Warsaw University of Life Sciences and used rooms made available, among others, by the Ministry of National Defense. Therefore, after analyzing information about available properties, the National Prosecutor purchased a developed property at ul. on the secondary market. Postępu 3 in Warsaw.

“He made the decision to purchase despite the lack of a reliable assessment of the technical condition of the property and a reliable estimate of the expenditure necessary to adapt it to the needs of the National Prosecutor's Office. Due to the lack of offers, the Prosecutor's Office refrained from commissioning a preliminary assessment of the technical condition of the property to specialists and entrusted these tasks to specialists. employees of the National Prosecutor's Office who did not have the required authorizations,” the Supreme Audit Office reported, concluding that the National Prosecutor's Office did not have reliable information about the efficiency of the installations and devices in the building.

“The estimate of the expenditure necessary to adapt the purchased buildings to the needs of the National Prosecutor's Office was based on unrealistic assumptions, because the planned costs increased more than fourfold from PLN 15 million to PLN 76.1 million (more than fivefold – ed.),” the Chamber reported. She also added that the inspection showed that the estimated cost of the investment was established unreliably, which led to the underestimation of the actual costs of adapting the buildings to the needs of the PK.

Renovation works and NIK reservations

Moreover, NIK pointed out that most of the renovation works were commissioned to the Prison Work Establishment of the Mazovian Budgetary Management Institution “Mazovia”.

“Mazovia” – as reported by the Supreme Audit Office – did not have the equipment to carry out such an investment, so it commissioned the work to three subcontractors. “For the implementation of contracts commissioned by 'Mazovia' to subcontractors, the Prosecutor's Office paid PLN 29.5 million, i.e. PLN 3.7 million more than the costs incurred by 'Mazovia', which amounted to PLN 25.8 million, of which only PLN 103.2 thousand were the costs of works carried out independently by persons deprived of their liberty,” we read in the release.

NIK also found it disturbing that despite the completion of the general reconstruction of the PK headquarters in 2020, for which PLN 76.1 million was spent, already in 2022 some elements and installations were in poor technical condition.

In the summary of information about irregularities in this case, the Supreme Audit Office stated that it had formulated post-audit conclusions which oblige the National Prosecutor's Office – as we read in the press release – “in particular to make a reliable assessment of the condition of the purchased properties before the purchase and to reliably estimate the amount of expenditure necessary for renovation and to manage the funds economically.” public”.

There is an investigation

Due to the Supreme Audit Office's audit, an investigation was initiated at the Regional Prosecutor's Office in Warsaw. In the course of the proceedings, which began on April 30 this year, threads regarding irregularities related to the spending of funds in this case are being investigated.

– At the current stage of the investigation, documentation regarding the investment and materials from the inspection carried out by the Supreme Audit Office have been collected and analyzed, and witnesses are being questioned in the case – said on Wednesday the spokesman for the Regional Prosecutor's Office in Warsaw, Prosecutor Mirosław Jerzy Iwanicki.

The prosecutor's office is investigating the planning and adaptation of the premises of the new PK headquarters at ul. Postępu 3 in Warsaw “without assessing the technical condition and the amount of expenditure necessary for the renovation of this property.” It is also investigating the violation of the Public Procurement Law in connection with proceedings for the award of public contracts for construction works, which were carried out on the basis of contracts between PK and “Mazovia”.

In addition, the prosecutor's office is dealing with the issue of renovation of office space and purchase of equipment at the PK headquarters in Warsaw at ul. Rakowiecka 26/30 and Nowowiejska 26B, despite – as also reported by the Supreme Audit Office – the decision to change the registered office, as well as the case of failure to pursue claims for contractual penalties from the audit supervision and the substitute investor.