Warsaw. TBM shields Anna and Krystyna will drill subway tunnels. They are on Karolina. Construction of the second metro line

Must read

- Advertisement -


TBM shields weighing 650 tons, named Anna and Krystyna, arrived in the Karolin Islands. Once assembled, they will begin drilling the four-kilometer Bemowo section of the second metro line. They will work 24 hours a day. Lazurowa, Chrzanów and Karolin stations should welcome the first passengers in 2026.

The Warsaw TBM shields weigh over 650 tons, are almost 100 meters long and have a diameter of over six meters each. After completing the tunneling work, the M2 line was inspected and renovated.

TBM shields at the Karolin metro station Warsaw Metro

3,800 rings to arrange

- Advertisement -

Now the shields Anna and Krystyna set off to continue working on tunneling the missing section of the M2 line. The first elements of both shields arrived at the Karolin metro station by special night transport. It is from there that the construction of the underground route towards the Bemowo station will begin. The installation of the shields will be carried out directly in the so-called the starting shaft, i.e. where the tunnel drilling will begin. During the following nights, the TBM shield elements will be transported by special transport to the construction site.

Read also: The metro will end here. You can already see the construction of a huge “garage” >>>

TBM shields at the Karolin metro station Warsaw Metro

The length of the tunnels of the western section of the second metro line is: 3,202 meters and 3,196 meters. “The TBM shields will therefore have to be placed in 3,800 prefabricated rings, each 1.5 meters long. The drilling is scheduled to start during the summer holidays. The cutting machines will work 24 hours a day from the moment they are launched. The only condition for stopping the work is a problem with the ground or with the machine itself or replacing the cutting blades,” the town hall said.

The TBM shield is fully mechanized, but human presence is required. Its work is supervised by a 12-person crew who work in four shifts. The TBM is driven by 16 pairs of hydraulic cylinders.

TBM shields at the Karolin metro station Warsaw Metro

Read also: Bones on the construction site of the second metro line >>>

Three stations by 2026

Three stations have been designed on the almost four-kilometer Bemowo section of the second metro line.

Lazurowa Station is being built on the south-eastern side of the intersection of Lazurowa and Górczewska, between the tram terminus and Lazurowa. The Chrzanów station is planned under Rayskiego Street, near the intersection with Szeligowska.

TBM shields at the Karolin metro station Warsaw Metro

Karolin station is located under Sochaczewska Street, on the northern side of the intersection with Połczyńska. Behind it, technical facilities for the entire line are being built – STP Karolin.

The contract worth PLN 1.9 billion is scheduled to be completed and put into service for passengers in 2026.

Main photo source: Warsaw Metro