Warsaw. The employees returned to the construction of the subway in Bemowo. Did you manage to sign an annex with the town hall?

Must read

- Advertisement -


The Warsaw metro boasted of progress on the construction of the underground railway in Bemowo. At the end of May, the contractor stopped work there. Although there was official talk of a “reorganization of the construction site”, there was a conflict in the background over an unsigned annex between the company and the city. As we found out, “the annex should be signed in the coming days.”

“Work is underway on the construction of the newest section of the metro in Bemowo. In the area where the C01 Karolin and C03 Lazurowa stations will be built, diaphragm walls of future entrances to the stops are being built. Barrettes, i.e. deep foundations supporting both temporary poles and target poles that will support the ceilings of the station,” the metro representatives wrote on Facebook.

On the other hand, earthworks are underway at the construction site of the Karolin Technical and Parking Station, including excavations for future facilities such as the administration building or the electric locomotive depot, they added and posted photos.

At the end of May, construction work was suspended

- Advertisement -

Recall, at the end of the year, Rafał Trzaskowski, the mayor of Warsaw informed about the agreement that the town hall managed to work out with the contractor for the construction of the second metro line in Bemowo. The latter wanted to update the contract due to rising material costs. Under this contract, three stations are being built: Lazurowa, Chrzanów and Karolin, as well as a technical and parking station.

However, at the end of May, half a year after the announcement of success, the annex was still not signed, and on the construction site of the Chrzanów station, as a resident reported to us, “nothing was happening”.

At that time, the contractor only told us about the “reorganization of the construction site”, but the deputy mayor of Warsaw admitted that “part of the contract” was suspended.

Does the return of employees to the construction site mean that the annex has been signed? – In recent days, the works have been significantly accelerated, we have received a guarantee from the city and the subway that all technical issues related to the annex have already been resolved and it should be signed in the coming days, the document is undergoing final inspections – Bartosz Sawicki, the contractor’s spokesman, told us.

Main photo source: Warsaw Metro