This year, the second stage of construction of the Mokotowski-Bis collector is to start. The network will run under the Vistula. Difficulties related to work will fall on 2026 and 2027. As the water supply, traffic on the route assures, though there will be local narrowing.
The president of Warsaw Waterworks Renata Tomusiak emphasized that this collector episode will be three times longer than the already built section under Gagarina. Construction will last three years. The collector will run under the Wisłostrada. It will start at the intersection of Czerniakowska and Gagarin. Then he will run Czerniakowska and a piece of Solec, end with the landing plate.
The planned investment cost is over PLN 304 million. After its completion, the total collector capacity will be 17,000 cubic meters.
Construction using a trenchless method
– This year we will choose the contractor and we will take action – said Tomusiak. She noted that the nuisance related to construction will fall for 2026 and 2027.
The water supply reported that the construction of the collector would be carried out by a trenchless method. The works will be carried out mainly within the start and receiving chambers. Waterworks declare that during this time the traffic on Wisłostrada will be maintained (at least two lanes are to be passable), although there will be restrictions on short sections.
In 2025, Gruba Kaśka will also undergo modernization, and the modernization of the Bielański collector will be completed.
Millions for various tasks
For 2025, water supply people have PLN 676.5 million in the economic plan. Including linear tasks (construction of water and sewage network) 404, PLN 1 million, and for cubature tasks (e.g. further modernization of plants) PLN 162.2 million. Waterworks will build over 100 kilometers of network for this money. Most investments will be in Wawra and Białołęka.
In total, as a result of the implementation of 293 tasks in the construction and modernization of the water supply and sewage network planned for 2025, it will be possible to connect 3144 new address points, including as a result of 186 tasks planned for completing the implementation in 2025, it will be possible to connect 1963 new address points.
Author/author: mg/b